ITAC Assessment: IP0166
ITAC logo
ITAC Assessment: IP0166
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Winemaking
NAICS 312130: Wineries
SIC 2082: Malt Beverages
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 106,000
ft2
Annual Production 1,800
Tgal
Production Hrs. Annual 2,860
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,017 1,735,577
kWh
Electricity Demand $83,159 5,777
kW-mo/yr
Electricity Fees $13,724 -
LPG $161,874 7,723
MMBtu
Waste Disposal Costs
Water Usage $23,890 3,153
Tgal
TOTAL YEARLY COSTS $378,664
RECOMMENDED SAVINGS* $49,570 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,866

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings
01 2.2625: Chill water to the highest temperature possible $12,766 - $5,793
96,554
kWh
$6,973
-
kW-mo/yr
- -
02 2.2625: Chill water to the highest temperature possible $4,102 - $1,609
32,178
kWh
$2,493
-
kW-mo/yr
- -
03 2.2625: Chill water to the highest temperature possible $9,132 - $3,615
72,301
kWh
$5,517
-
kW-mo/yr
- -
04 2.7224: Reduce space conditioning during non-working hours $2,623 - $863
7,847
kWh
- - $1,760
-
MMBtu
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $526 $33 $526
10,512
kWh
- - -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,625 $3,274 $6,625
110,417
kWh
- - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,433 $1,162 $1,433
28,660
kWh
- - -
08 2.2437: Recover waste heat from equipment $704 $1,279 - - - $704
-
MMBtu
09 2.7142: Utilize higher efficiency lamps and/or ballasts $198 $416 $198
1,789
kWh
- - -
10 2.4221: Install compressor air intakes in coolest locations $279 $665 $134
2,689
kWh
$145
-
kW-mo/yr
- -
11 2.3212: Optimize plant power factor $11,046 $43,200 - - $11,046 -
12 2.4221: Install compressor air intakes in coolest locations $136 $665 $65
1,302
kWh
$71
-
kW-mo/yr
- -
TOTAL RECOMMENDED $49,570 $50,694 $20,861
364,249
kWh
$15,199
-
kW-mo/yr
$11,046 $2,464
-
MMBtu
TOTAL IMPLEMENTED $22,866 $49,415 $9,844
163,216
kWh
$216
-
kW-mo/yr
$11,046 $1,760
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs