Assessment Year | 2004 |
---|---|
Principal Product | Processed Fruit |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2030: |
Sales Range | $10 M to 50M |
# of Employees | 152 |
Plant Area |
100,000
ft2
|
Annual Production | 80,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $348,884 | 6,408,000 |
kWh
|
$0.054 |
Electricity Demand | $167,416 | 18,960 |
kW-mo/yr
|
$8.83 |
LPG | $232,611 | 22,859 |
MMBtu
|
$10.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $133,176 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $124,014 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $839 | - |
$565
11,315
kWh
|
$274
-
kW-mo/yr
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $99,155 | $3,104 |
$72,930
1,458,600
kWh
|
$26,225
-
kW-mo/yr
|
- | |
03 | 2.7261: Install timers and/or thermostats | $3,889 | $896 | - | - |
$3,889
-
MMBtu
|
|
04 | 3.4151: Minimize water usage | $1,683 | $427 |
$350
7,000
kWh
|
- |
$1,333
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,174 | $6,679 |
$5,525
110,500
kWh
|
$2,649
-
kW-mo/yr
|
- | |
06 | 2.2442: Preheat combustion air with waste heat | $9,764 | $8,647 | - | - |
$9,764
-
MMBtu
|
|
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $510 | $468 |
$375
7,514
kWh
|
$135
-
kW-mo/yr
|
- | |
08 | 3.6122: Install solid waste incinerator for heat | $9,162 | $8,765 | - | - |
$9,162
-
MMBtu
|
|
TOTAL RECOMMENDED | $133,176 | $28,986 |
$79,745
1,594,929
kWh
|
$29,283
-
kW-mo/yr
|
$24,148
-
MMBtu
|
||
TOTAL IMPLEMENTED | $124,014 | $20,221 |
$79,745
1,594,929
kWh
|
$29,283
-
kW-mo/yr
|
$14,986
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs