Assessment Year | 2003 |
---|---|
Principal Product | motors |
NAICS | 335312: Motor and Generator Manufacturing |
SIC | 3621: Motors and Generators |
Sales Range | $1 M to 5M |
# of Employees | 100 |
Plant Area |
68,000
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 2,250
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $67,791 | 801,159 |
kWh
|
$0.085 |
Electricity Demand | $49,753 | 3,591 |
kW-mo/yr
|
$13.85 |
Natural Gas | $79,522 | 69,812 |
MMBtu
|
$1.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,054 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,289 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.311: Schedule deliveries according to demand | $4,883 | - | - | - | - | - | $4,883 | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,000 | - |
$1,066
12,600
kWh
|
$934
-
kW-mo/yr
|
- | - | - | |
03 | 2.6218: Turn off equipment when not in use | $515 | - |
$421
4,980
kWh
|
$94
-
kW-mo/yr
|
- | - | - | |
04 | 4.821: Pay bills on time to avoid late fees | $325 | - | - | - | $325 | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,426 | $120 |
$761
9,000
kWh
|
$665
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,140 | $400 |
$1,142
13,500
kWh
|
$998
-
kW-mo/yr
|
- | - | - | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $31,815 | $30,250 | - | - | - | - | $31,815 | |
08 | 2.2437: Recover waste heat from equipment | $1,950 | $4,508 | - | - | - |
$1,950
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $45,054 | $35,278 |
$3,390
40,080
kWh
|
$2,691
-
kW-mo/yr
|
$325 |
$1,950
-
MMBtu
|
$36,698 | ||
TOTAL IMPLEMENTED | $9,289 | $520 |
$2,324
27,480
kWh
|
$1,757
-
kW-mo/yr
|
$325 | - | $4,883 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs