Assessment Year | 2003 |
---|---|
Principal Product | Remanufactured Office Furniture |
NAICS | 337211: Wood Office Furniture Manufacturing |
SIC | 2521: Wood Office Furniture |
Sales Range | $5 M to 10M |
# of Employees | 30 |
Plant Area |
75,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $24,288 | 268,800 |
kWh
|
$0.090 |
Electricity Demand | $11,854 | 1,444 |
kW-mo/yr
|
$8.21 |
Natural Gas | $26,436 | 32,877 |
MMBtu
|
$0.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $74,876 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $57,422 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,694 | - |
$1,766
19,622
kWh
|
$928
-
kW-mo/yr
|
- | |
02 | 4.111: Add equipment/ operators to reduce production bottleneck | $53,040 | $348 | - | - | $53,040 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,194 | $26 |
$783
8,695
kWh
|
$411
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $494 | $168 |
$322
3,578
kWh
|
$172
-
kW-mo/yr
|
- | |
05 | 4.431: Train operators for maximum operating efficiency | $10,608 | $9,520 | - | - | $10,608 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,846 | $7,106 |
$4,744
52,708
kWh
|
$2,102
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $74,876 | $17,168 |
$7,615
84,603
kWh
|
$3,613
-
kW-mo/yr
|
$63,648 | ||
TOTAL IMPLEMENTED | $57,422 | $542 |
$2,871
31,895
kWh
|
$1,511
-
kW-mo/yr
|
$53,040 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs