ITAC Assessment: SU0169
ITAC logo
ITAC Assessment: SU0169
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Remanufactured Office Furniture
NAICS 337211: Wood Office Furniture Manufacturing
SIC 2521: Wood Office Furniture
Sales Range $5
M
to 10
M
# of Employees 30
Plant Area 75,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,080
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $24,288 268,800
kWh
Electricity Demand $11,854 1,444
kW-mo/yr
Natural Gas $26,436 32,877
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $74,876 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,422

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,694 - $1,766
19,622
kWh
$928
-
kW-mo/yr
-
02 4.111: Add equipment/ operators to reduce production bottleneck $53,040 $348 - - $53,040
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,194 $26 $783
8,695
kWh
$411
-
kW-mo/yr
-
04 2.4221: Install compressor air intakes in coolest locations $494 $168 $322
3,578
kWh
$172
-
kW-mo/yr
-
05 4.431: Train operators for maximum operating efficiency $10,608 $9,520 - - $10,608
06 2.7142: Utilize higher efficiency lamps and/or ballasts $6,846 $7,106 $4,744
52,708
kWh
$2,102
-
kW-mo/yr
-
TOTAL RECOMMENDED $74,876 $17,168 $7,615
84,603
kWh
$3,613
-
kW-mo/yr
$63,648
TOTAL IMPLEMENTED $57,422 $542 $2,871
31,895
kWh
$1,511
-
kW-mo/yr
$53,040
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs