Assessment Year | 1998 |
---|---|
Principal Product | baked beans |
NAICS |
n/a
|
SIC | 2032: Canned Specialties |
Sales Range | greater than $500 M |
# of Employees | 210 |
Plant Area |
107,000
ft2
|
Annual Production | 648,000,000
pieces
|
Production Hrs. Annual | 4,992
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $173,802 | 2,368,992 |
kWh
|
$0.073 |
Electricity Demand | $60,821 | 10,274 |
kW-mo/yr
|
$5.92 |
Electricity Fees | $11,642 | - |
|
- |
Natural Gas | $230,867 | 60,509 |
MMBtu
|
$3.82 |
Fuel Oil #6 | $242,370 | 76,942 |
MMBtu
|
$3.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $102,612 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,516 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #6 Savings | Water Disposal Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,669 | $38,422 |
$12,994
185,815
kWh
|
$1,675
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 4.652: Replace existing equipment with more suitable substitutes | $12,523 | $22,943 | - | - |
$12,523
-
MMBtu
|
- | - | - | - | |
03 | 2.2136: Install / repair insulation on steam lines | $14,710 | $12,260 | - | - | - |
$14,710
-
MMBtu
|
- | - | - | |
04 | 4.231: Purchase equipment instead of leasing | $5,602 | $7,719 |
$(-2,209.0)
(-31,360)
kWh
|
$(-509.0)
-
kW-mo/yr
|
- | - | - | $8,320 | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,877 | $500 |
$1,877
26,671
kWh
|
- | - | - | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $444 | $804 |
$366
5,275
kWh
|
$78
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.4239: Eliminate or reduce compressed air usage | $214 | $250 |
$214
2,931
kWh
|
- | - | - | - | - | - | |
08 | 3.4115: Recover and reuse cooling water | $47,833 | $131,000 |
$(-11,850.0)
(-168,816)
kWh
|
$(-3,167.0)
-
kW-mo/yr
|
- | - | - | $(-8,150.0) |
$71,000
-
Tgal
|
|
09 | 3.4151: Minimize water usage | $2,419 | $8,000 |
$(-875.0)
(-12,603)
kWh
|
- | - | - |
$2,904
-
Tgal
|
- |
$390
-
Tgal
|
|
10 | 3.4158: Use minimum cooling water to bearings | $2,321 | $4,200 | - | - | - |
$1,835
-
MMBtu
|
- | - |
$486
-
Tgal
|
|
TOTAL RECOMMENDED | $102,612 | $226,098 |
$517
7,913
kWh
|
$(-1,923.0)
-
kW-mo/yr
|
$12,523
-
MMBtu
|
$16,545
-
MMBtu
|
$2,904
-
Tgal
|
$170 |
$71,876
-
Tgal
|
||
TOTAL IMPLEMENTED | $37,516 | $59,955 |
$13,242
189,332
kWh
|
$1,244
-
kW-mo/yr
|
- |
$14,710
-
MMBtu
|
- | $8,320 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #6 Savings | Water Disposal Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs