ITAC Assessment: ME0241
ITAC logo
ITAC Assessment: ME0241
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product baked beans
NAICS
n/a
SIC 2032: Canned Specialties
Sales Range greater than $500
M
# of Employees 210
Plant Area 107,000
ft2
Annual Production 648,000,000
pieces
Production Hrs. Annual 4,992
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $173,802 2,368,992
kWh
Electricity Demand $60,821 10,274
kW-mo/yr
Electricity Fees $11,642 -
Natural Gas $230,867 60,509
MMBtu
Fuel Oil #6 $242,370 76,942
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $102,612 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,516

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #6 Savings Water Disposal Savings Administrative Changes Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,669 $38,422 $12,994
185,815
kWh
$1,675
-
kW-mo/yr
- - - - -
02 4.652: Replace existing equipment with more suitable substitutes $12,523 $22,943 - - $12,523
-
MMBtu
- - - -
03 2.2136: Install / repair insulation on steam lines $14,710 $12,260 - - - $14,710
-
MMBtu
- - -
04 4.231: Purchase equipment instead of leasing $5,602 $7,719 $(-2,209.0)
(-31,360)
kWh
$(-509.0)
-
kW-mo/yr
- - - $8,320 -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,877 $500 $1,877
26,671
kWh
- - - - - -
06 2.4133: Use most efficient type of electric motors $444 $804 $366
5,275
kWh
$78
-
kW-mo/yr
- - - - -
07 2.4239: Eliminate or reduce compressed air usage $214 $250 $214
2,931
kWh
- - - - - -
08 3.4115: Recover and reuse cooling water $47,833 $131,000 $(-11,850.0)
(-168,816)
kWh
$(-3,167.0)
-
kW-mo/yr
- - - $(-8,150.0) $71,000
-
Tgal
09 3.4151: Minimize water usage $2,419 $8,000 $(-875.0)
(-12,603)
kWh
- - - $2,904
-
Tgal
- $390
-
Tgal
10 3.4158: Use minimum cooling water to bearings $2,321 $4,200 - - - $1,835
-
MMBtu
- - $486
-
Tgal
TOTAL RECOMMENDED $102,612 $226,098 $517
7,913
kWh
$(-1,923.0)
-
kW-mo/yr
$12,523
-
MMBtu
$16,545
-
MMBtu
$2,904
-
Tgal
$170 $71,876
-
Tgal
TOTAL IMPLEMENTED $37,516 $59,955 $13,242
189,332
kWh
$1,244
-
kW-mo/yr
- $14,710
-
MMBtu
- $8,320 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #6 Savings Water Disposal Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs