ITAC Assessment: SU0161
ITAC logo
ITAC Assessment: SU0161
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Boilers
NAICS 333414: Heating Equipment (except Warm Air Furnaces) Manufacturing
SIC 4334:
Sales Range $10
M
to 50
M
# of Employees 202
Plant Area 140,000
ft2
Annual Production 2,500
pieces
Production Hrs. Annual 4,420
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $195,170 1,925,933
kWh
Natural Gas $73,846 10,419
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,202 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,038

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $12,003 $16,100 - - $12,003
-
MMBtu
02 2.1133: Adjust burners for efficient operation $1,035 $540 - - $1,035
-
MMBtu
03 2.2136: Install / repair insulation on steam lines $580 $2,033 - - $580
-
MMBtu
04 2.4221: Install compressor air intakes in coolest locations $531 $1,608 $165
5,501
kWh
$366
-
kW-mo/yr
-
05 2.2437: Recover waste heat from equipment $468 $748 - - $468
-
MMBtu
06 2.4314: Use synthetic lubricant $272 $800 $121
4,036
kWh
$151
-
kW-mo/yr
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $218 - $101
3,359
kWh
$117
-
kW-mo/yr
-
08 2.7135: Install occupancy sensors $95 $70 $95
3,182
kWh
- -
TOTAL RECOMMENDED $15,202 $21,899 $482
16,078
kWh
$634
-
kW-mo/yr
$14,086
-
MMBtu
TOTAL IMPLEMENTED $13,038 $16,640 - - $13,038
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs