ITAC Assessment: SU0147
ITAC logo
ITAC Assessment: SU0147
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Blow Molded Parts
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area 91,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,240
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $185,954 2,790,240
kWh
Electricity Demand $95,554 7,117
kW-mo/yr
Electricity Fees $5,437 -
Natural Gas $15,694 1,810
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,771 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $6,867 $39,847 $4,933
73,630
kWh
$1,934
-
kW-mo/yr
- -
02 2.7243: Improve air circulation with destratification fans / other methods $4,126 $7,590 $(-965.0)
(-14,400)
kWh
$258
-
kW-mo/yr
- $4,833
-
MMBtu
03 2.2437: Recover waste heat from equipment $3,432 $2,288 - - - $3,432
-
MMBtu
04 2.3212: Optimize plant power factor $2,974 $8,850 - - $2,974 -
05 2.4239: Eliminate or reduce compressed air usage $2,193 $1,528 $2,193
32,731
kWh
- - -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,104 $5,675 $2,104
31,409
kWh
- - -
07 2.4221: Install compressor air intakes in coolest locations $1,381 $437 $1,381
20,613
kWh
- - -
08 2.7111: Reduce illumination to minimum necessary levels $694 $196 $315
4,704
kWh
$379
-
kW-mo/yr
- -
TOTAL RECOMMENDED $23,771 $66,411 $9,961
148,687
kWh
$2,571
-
kW-mo/yr
$2,974 $8,265
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs