Assessment Year | 2002 |
---|---|
Principal Product | paper products |
NAICS |
n/a
|
SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
170,000
ft2
|
Annual Production | 1,000,000,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $53,136 | 806,400 |
kWh
|
$0.066 |
Electricity Demand | $62,730 | 4,190 |
kW-mo/yr
|
$14.97 |
Electricity Fees | $7,451 | - |
|
- |
Natural Gas | $49,424 | 7,109 |
MMBtu
|
$6.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $52,535 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,562 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.811: Demolish old building to reduce tax and insurance bills | $18,266 | $35,000 |
$55
832
kWh
|
$72
-
kW-mo/yr
|
- |
$18,139
-
MMBtu
|
- | - | |
02 | 3.5217: Reuse / recycle/ sell paper products | $16,051 | $38,750 | - | - | - |
$16,051
-
MMBtu
|
- | - | |
03 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $6,273 | $61,828 | - | - | - |
$6,273
-
MMBtu
|
- | - | |
04 | 4.114: Add/modify equipment to improve drying process | $4,723 | $420 |
$(-685.0)
(-10,400)
kWh
|
- | - | - | - | $5,408 | |
05 | 2.4239: Eliminate or reduce compressed air usage | $4,500 | $852 |
$4,500
68,289
kWh
|
- | - | - | - | - | |
06 | 3.4114: Replace city water with recycled water via cooling tower | $799 | $1,690 |
$(-39.0)
(-597)
kWh
|
- | - | - |
$838
-
Tgal
|
- | |
07 | 2.8123: Pay utility bills on time | $791 | - | - | - | $791 | - | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $494 | - |
$494
7,500
kWh
|
- | - | - | - | - | |
09 | 2.7135: Install occupancy sensors | $383 | $288 |
$383
5,816
kWh
|
- | - | - | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $255 | $11 |
$255
3,867
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $52,535 | $138,839 |
$4,963
75,307
kWh
|
$72
-
kW-mo/yr
|
$791 |
$40,463
-
MMBtu
|
$838
-
Tgal
|
$5,408 | ||
TOTAL IMPLEMENTED | $11,562 | $2,973 |
$4,525
68,659
kWh
|
- | $791 | - |
$838
-
Tgal
|
$5,408 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs