ITAC Assessment: SU0138
ITAC logo
ITAC Assessment: SU0138
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product material handeling equipment for the wire and fiber optic industries
NAICS
n/a
SIC 3500:
Sales Range $10
M
to 50
M
# of Employees 43
Plant Area 70,000
ft2
Annual Production 63
pieces
Production Hrs. Annual 2,080
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $53,510 687,106
kWh
Other Energy $92,885 18,577
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $115,942 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,082

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Other Energy Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $4,127 $1,445 - $4,127
-
MMBtu
02 2.4231: Reduce the pressure of compressed air to the minimum required $939 - $939
12,320
kWh
-
03 2.7111: Reduce illumination to minimum necessary levels $5,706 - $5,706
63,866
kWh
-
04 2.7111: Reduce illumination to minimum necessary levels $6,391 - $6,391
74,880
kWh
-
05 4.452: Eliminate shift $10,752 - $4,156
29,688
kWh
$6,596
-
MMBtu
06 2.1392: Replace purchased steam with other energy source $88,027 $55,497 - $88,027
-
MMBtu
TOTAL RECOMMENDED $115,942 $56,942 $17,192
180,754
kWh
$98,750
-
MMBtu
TOTAL IMPLEMENTED $18,082 - $11,486
116,888
kWh
$6,596
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Other Energy Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs