Assessment Year | 2002 |
---|---|
Principal Product | Thermoformed Plastics |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 28 |
Plant Area |
40,000
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $104,932 | 1,182,500 |
kWh
|
$0.089 |
Electricity Demand | $84,439 | 7,123 |
kW-mo/yr
|
$11.85 |
Natural Gas | $33,384 | 3,255 |
MMBtu
|
$10.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,882 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,814 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8118: Check for accuracy of utility / power meters | $482 | - | - | - | $482 | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,025 | - |
$1,025
11,387
kWh
|
- | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $339 | $115 |
$339
3,766
kWh
|
- | - | - | - | |
04 | 2.2135: Repair and eliminate steam leaks | $675 | $87 |
$675
7,500
kWh
|
- | - | - | - | |
05 | 2.2511: Insulate bare equipment | $754 | $322 | - | - | - |
$754
-
MMBtu
|
- | |
06 | 2.2511: Insulate bare equipment | $1,110 | $264 | - | - | - |
$1,110
-
MMBtu
|
- | |
07 | 2.2511: Insulate bare equipment | $2,774 | $495 |
$2,774
30,823
kWh
|
- | - | - | - | |
08 | 2.7135: Install occupancy sensors | $123 | $60 |
$123
1,212
kWh
|
- | - | - | - | |
09 | 2.2437: Recover waste heat from equipment | $314 | $460 | - | - | - |
$314
-
MMBtu
|
- | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $14 | - |
$8
82
kWh
|
$6
-
kW-mo/yr
|
- | - | - | |
11 | 4.111: Add equipment/ operators to reduce production bottleneck | $3,402 | $13,000 | - | - | - | - | $3,402 | |
12 | 4.111: Add equipment/ operators to reduce production bottleneck | $5,870 | $4,230 | - | - | - | - | $5,870 | |
TOTAL RECOMMENDED | $16,882 | $19,033 |
$4,944
54,770
kWh
|
$6
-
kW-mo/yr
|
$482 |
$2,178
-
MMBtu
|
$9,272 | ||
TOTAL IMPLEMENTED | $6,814 | $1,343 |
$4,944
54,770
kWh
|
$6
-
kW-mo/yr
|
- |
$1,864
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs