Assessment Year | 1997 |
---|---|
Principal Product | truck/trailer van bodies |
NAICS |
n/a
|
SIC | 3713: Truck and Bus Bodies |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
39,000
ft2
|
Annual Production | 1,050
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $14,534 | 799,531 |
kWh
|
$0.018 |
Electricity Demand | $37,689 | 2,651 |
kW-mo/yr
|
$14.22 |
Electricity Fees | $146 | - |
|
- |
Natural Gas | $22,893 | 5,099 |
MMBtu
|
$4.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,262 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $38,242 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $4,570 | $1,000 | - |
$4,570
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,292 | $1,356 |
$288
15,826
kWh
|
$1,004
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,220 | $420 |
$270
14,654
kWh
|
$950
-
kW-mo/yr
|
- | - | - | |
04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $630 | - | - | - |
$630
-
lb
|
- | - | |
05 | 3.6192: Use a less expensive method of waste removal | $450 | - | - | - | - |
$450
-
lb
|
- | |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $35,100 | $1,800 | - | - | - | - | $35,100 | |
TOTAL RECOMMENDED | $43,262 | $4,576 |
$558
30,480
kWh
|
$6,524
-
kW-mo/yr
|
$630
-
lb
|
$450
-
lb
|
$35,100 | ||
TOTAL IMPLEMENTED | $38,242 | $3,576 |
$558
30,480
kWh
|
$1,954
-
kW-mo/yr
|
$630
-
lb
|
- | $35,100 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs