ITAC Assessment: SU0130
ITAC logo
ITAC Assessment: SU0130
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Wood pallets and boxes
NAICS
n/a
SIC 2448: Wood Pallets and Skids
Sales Range $1
M
to 5
M
# of Employees 70
Plant Area 61,509
ft2
Annual Production 200,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $50,078 767,550
kWh
Electricity Demand $46,510 3,417
kW-mo/yr
Other Gas $920 60
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $146,095 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $524

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Wood Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $217 $518 $217
3,103
kWh
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $307 $38 $307
4,386
kWh
- -
03 2.4221: Install compressor air intakes in coolest locations $442 $871 $442
6,317
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,614 $1,875 $1,763
25,182
kWh
$851
-
kW-mo/yr
-
05 4.131: Modify process to reduce material use/cost $33,055 $2,330 $11
162
kWh
- $33,044
-
MMBtu
06 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat $109,460 $1,150,000 $53,729
767,560
kWh
$55,731
-
kW-mo/yr
-
TOTAL RECOMMENDED $146,095 $1,155,632 $56,469
806,710
kWh
$56,582
-
kW-mo/yr
$33,044
-
MMBtu
TOTAL IMPLEMENTED $524 $556 $524
7,489
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Wood Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs