Assessment Year | 2001 |
---|---|
Principal Product | bearing assemblies |
NAICS |
n/a
|
SIC | 3562: Ball and Roller Bearings |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
220,000
ft2
|
Annual Production | 130,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $211,064 | 7,764,370 |
kWh
|
$0.027 |
Electricity Demand | $173,409 | 25,887 |
kW-mo/yr
|
$6.70 |
Electricity Fees | $18,197 | - |
|
- |
Natural Gas | $393,634 | 51,376 |
MMBtu
|
$7.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,447 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,106 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.821: Pay bills on time to avoid late fees | $1,106 | - | - | - | - | - | $1,106 | |
02 | 2.3212: Optimize plant power factor | $2,537 | $8,750 | - | - | $2,537 | - | - | |
03 | 2.7135: Install occupancy sensors | $188 | $30 |
$188
6,268
kWh
|
- | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $160 | $840 |
$118
3,942
kWh
|
$42
-
kW-mo/yr
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,600 | - |
$3,600
120,000
kWh
|
- | - | - | - | |
06 | 2.7293: Install dry sprinkler system or other method to reduce heating requirements | $21,289 | $75,000 |
$540
18,000
kWh
|
$67
-
kW-mo/yr
|
- |
$20,682
-
MMBtu
|
- | |
07 | 2.4226: Use / purchase optimum sized compressor | $12,567 | $20,000 |
$12,567
418,900
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $41,447 | $104,620 |
$17,013
567,110
kWh
|
$109
-
kW-mo/yr
|
$2,537 |
$20,682
-
MMBtu
|
$1,106 | ||
TOTAL IMPLEMENTED | $1,106 | - | - | - | - | - | $1,106 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs