Assessment Year | 1986 |
---|---|
Principal Product | EMBROIDERED EMBLEMS |
NAICS |
n/a
|
SIC | 2399: Fabricated Textile Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 40,000,000
pieces
|
Production Hrs. Annual | 4,375
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $105,285 | 1,167,057 |
kWh
|
$0.090 |
Natural Gas | $14,628 | 1,887 |
MMBtu
|
$7.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,673 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,354 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $2,257 | $6,000 |
$2,257
-
kWh
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $1,295 | $2,833 |
$1,295
14,361
kWh
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $106 | $46 |
$106
1,172
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $502 | $110 |
$502
5,569
kWh
|
- | |
05 | 2.7226: Use computer programs to optimize hvac performance | $8,933 | $15,000 |
$8,933
99,062
kWh
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,982 | - |
$1,982
21,981
kWh
|
- | |
07 | 2.7229: Air condition only space necessary | $1,956 | - |
$1,956
21,688
kWh
|
- | |
08 | 2.7261: Install timers and/or thermostats | $4,642 | $300 | - |
$4,642
-
MMBtu
|
|
TOTAL RECOMMENDED | $21,673 | $24,289 |
$17,031
163,833
kWh
|
$4,642
-
MMBtu
|
||
TOTAL IMPLEMENTED | $17,354 | $18,243 |
$12,712
140,973
kWh
|
$4,642
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs