| Assessment Year | 1986 |
|---|---|
| Principal Product | SUNDAE TOPPINGS |
| NAICS |
n/a
|
| SIC | 2064: Candy and Other Confectionery Products |
| Sales Range | $5 M to 10M |
| # of Employees | 55 |
| Plant Area |
n/a
|
| Annual Production | 500,000
pieces
|
| Production Hrs. Annual | 4,250
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $83,893 | 1,013,775 |
kWh
|
$0.083 |
| Natural Gas | $96,788 | 14,727 |
MMBtu
|
$6.57 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,350 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $8,261 | $1,000 | - |
$8,261
-
MMBtu
|
|
| 02 | 2.1123: Install automatic stack damper | $2,122 | $1,034 | - |
$2,122
-
MMBtu
|
|
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $796 | $537 | - |
$796
-
MMBtu
|
|
| 04 | 2.6121: Reduce hot water temperature to the minimum required | $123 | - | - |
$123
-
MMBtu
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $856 | - |
$856
10,258
kWh
|
- | |
| 06 | 2.4133: Use most efficient type of electric motors | $540 | $1,000 |
$540
6,448
kWh
|
- | |
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $463 | $93 |
$463
5,569
kWh
|
- | |
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $14,044 | - | - |
$14,044
-
MMBtu
|
|
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,145 | $233 |
$1,145
13,775
kWh
|
- | |
| TOTAL RECOMMENDED | $28,350 | $3,897 |
$3,004
36,050
kWh
|
$25,346
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs