Assessment Year | 1985 |
---|---|
Principal Product | METALIZED POLYESTER |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 61 |
Plant Area |
n/a
|
Annual Production | 600,000
lb
|
Production Hrs. Annual | 4,100
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $51,286 | 555,393 |
kWh
|
$0.092 |
Fuel Oil #4 | $55,753 | 8,996 |
MMBtu
|
$6.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,314 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,624 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #4 Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,854 | $7,389 |
$4,854
52,462
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $917 | $104 |
$917
9,965
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $343 | - |
$343
3,810
kWh
|
- | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $478 | $870 |
$706
7,620
kWh
|
$(-228.0)
-
MMBtu
|
- | |
05 | 2.2136: Install / repair insulation on steam lines | $1,556 | $1,020 | - | - |
$1,556
-
MMBtu
|
|
06 | 2.2437: Recover waste heat from equipment | $391 | $900 | - | - |
$391
-
MMBtu
|
|
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,510 | $537 | - | - |
$2,510
-
MMBtu
|
|
08 | 2.7441: Replace broken windows and/or window sash | $3,038 | $935 | - | - |
$3,038
-
MMBtu
|
|
09 | 2.2414: Use waste heat from hot flue gases to preheat | $1,227 | $2,200 | - | - |
$1,227
-
MMBtu
|
|
TOTAL RECOMMENDED | $15,314 | $13,955 |
$6,820
73,857
kWh
|
$(-228.0)
-
MMBtu
|
$8,722
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,624 | $8,030 |
$6,114
66,237
kWh
|
- |
$2,510
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #4 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs