| Assessment Year | 2025 |
|---|---|
| Principal Product | Aircraft Engine and Parts Manufacturing |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 350 |
| Plant Area |
119,866
ft2
|
| Annual Production | 50,000
pieces
|
| Production Hrs. Annual | 3,250
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $152,648 | 1,732,569 |
kWh
|
$0.088 |
| Electricity Demand | $4,653 | 2,984 |
kW-mo/yr
|
$1.56 |
| Electricity Fees | $14,336 | - |
|
- |
| Natural Gas | $131,434 | 8,280 |
MMBtu
|
$15.87 |
| TOTAL YEARLY COSTS | $303,071 | |||
| RECOMMENDED SAVINGS* | $148,356 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $148,356 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $130,385 | $1,125,377 |
$129,679
1,471,951
kWh
|
$706
-
kW-mo/yr
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,759 | $18,648 |
$2,590
29,393
kWh
|
$169
-
kW-mo/yr
|
|
| 03 | 2.7135: Install occupancy sensors | $6,569 | $12,849 |
$6,569
74,568
kWh
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,643 | $25,000 |
$8,113
92,088
kWh
|
$530
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $148,356 | $1,181,874 |
$146,951
1,668,000
kWh
|
$1,405
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $148,356 | $1,181,874 |
$146,951
1,668,000
kWh
|
$1,405
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs