ITAC Assessment: ME0276
ITAC logo
ITAC Assessment: ME0276
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Men's shirts
NAICS
n/a
SIC 2321: Men's and Boys' Shirts, Except Work Shirts
Sales Range $10
M
to 50
M
# of Employees 425
Plant Area 280,760
ft2
Annual Production 130,000
pieces
Production Hrs. Annual 2,500
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $124,188 2,071,805
kWh
Electricity Demand $81,979 8,084
kW-mo/yr
Electricity Fees $4,419 -
Fuel Oil #6 $23,016 10,353
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,431 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #6 Savings Administrative Changes Savings
01 4.631: Install an uninteruptable power supply $6,000 $1,500 n/a - - - - $6,000
02 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $2,486 $1,468 n/a - - $2,486
-
MMBtu
- -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,395 - n/a - $491
-
kW-mo/yr
$1,087
-
MMBtu
$(-183.0)
-
MMBtu
-
04 2.4221: Install compressor air intakes in coolest locations $1,263 $400 n/a $1,263
21,102
kWh
- - - -
05 4.821: Pay bills on time to avoid late fees $1,075 - n/a - - - - $1,075
06 2.2511: Insulate bare equipment $520 $382 n/a - $420
-
kW-mo/yr
- $100
-
MMBtu
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $419 $300 n/a $419
7,034
kWh
- - - -
08 2.4133: Use most efficient type of electric motors $273 $994 n/a $273
4,689
kWh
- - - -
TOTAL RECOMMENDED $13,431 $5,044 $1,955
32,825
kWh
$911
-
kW-mo/yr
$3,573
-
MMBtu
$(-83.0)
-
MMBtu
$7,075
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #6 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs