Assessment Year | 1996 |
---|---|
Principal Product | Cable Assembly |
NAICS |
n/a
|
SIC | 3643: Current-Carrying Wiring Devices |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
88,000
ft2
|
Annual Production | 1,750,000
pieces
|
Production Hrs. Annual | 4,625
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,592 | 1,223,036 |
kWh
|
$0.080 |
Electricity Demand | $9,824 | 3,330 |
kW-mo/yr
|
$2.95 |
Natural Gas | $15,843 | 2,475 |
MMBtu
|
$6.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,534 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,534 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,768 | $13,765 |
$4,222
52,755
kWh
|
$546
-
kW-mo/yr
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $404 | $1,363 |
$367
4,689
kWh
|
$37
-
kW-mo/yr
|
- | |
03 | 2.6218: Turn off equipment when not in use | $436 | $432 |
$436
5,275
kWh
|
- | - | |
04 | 2.6218: Turn off equipment when not in use | $1,529 | $2,040 |
$1,428
17,878
kWh
|
$101
-
kW-mo/yr
|
- | |
05 | 2.2522: Isolate hot or cold equipment | $5,147 | $1,432 |
$4,867
60,961
kWh
|
$280
-
kW-mo/yr
|
- | |
06 | 3.5313: Increase amount of waste recovered for resale | $1,658 | $250 | - | - |
$1,658
-
lb
|
|
07 | 3.5316: Contract a wood pallet recycling company | $592 | $250 | - | - |
$592
-
lb
|
|
TOTAL RECOMMENDED | $14,534 | $19,532 |
$11,320
141,558
kWh
|
$964
-
kW-mo/yr
|
$2,250
-
lb
|
||
TOTAL IMPLEMENTED | $14,534 | $19,532 |
$11,320
141,558
kWh
|
$964
-
kW-mo/yr
|
$2,250
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs