Assessment Year | 1985 |
---|---|
Principal Product | FABRICATED STEEL |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $1 M to 5M |
# of Employees | 36 |
Plant Area |
n/a
|
Annual Production | 2,500
ton
|
Production Hrs. Annual | 0
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $20,890 | 170,281 |
kWh
|
$0.12 |
Natural Gas | $735 | 81 |
MMBtu
|
$9.07 |
Fuel Oil #1 | $7,920 | 679 |
MMBtu
|
$11.66 |
Fuel Oil #2 | $4,021 | 482 |
MMBtu
|
$8.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,694 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,404 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $514 | $64 |
$514
4,103
kWh
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $72 | $42 |
$72
586
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,640 | $688 |
$1,640
13,482
kWh
|
- | - | |
04 | 2.3191: Use demand controller or load shedder | $890 | $1,900 |
$890
-
kWh
|
- | - | |
05 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $1,974 | $900 |
$1,974
16,120
kWh
|
- | - | |
06 | 2.3311: Replace dc equipment with ac equipment | $2,416 | $5,000 |
$2,416
19,637
kWh
|
- | - | |
07 | 2.6121: Reduce hot water temperature to the minimum required | $305 | - |
$305
2,638
kWh
|
- | - | |
08 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $380 | $1,140 |
$550
4,396
kWh
|
$(-170.0)
-
MMBtu
|
- | |
09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $503 | $380 | - | - |
$503
-
MMBtu
|
|
TOTAL RECOMMENDED | $8,694 | $10,114 |
$8,361
60,962
kWh
|
$(-170.0)
-
MMBtu
|
$503
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,404 | $1,964 |
$1,404
4,103
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs