Assessment Year | 1985 |
---|---|
Principal Product | CAMERA,TAPE,& AUDIO CASE |
NAICS |
n/a
|
SIC | 3161: Luggage |
Sales Range | $10 M to 50M |
# of Employees | 316 |
Plant Area |
n/a
|
Annual Production | 4,000,000
pieces
|
Production Hrs. Annual | 2,353
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $136,959 | 754,982 |
kWh
|
$0.18 |
Natural Gas | $122,495 | 18,717 |
MMBtu
|
$6.54 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $99,058 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $35,251 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7229: Air condition only space necessary | $1,091 | $125 | - |
$1,091
-
MMBtu
|
- | |
02 | 2.1123: Install automatic stack damper | $8,365 | $26,400 | - |
$8,365
-
MMBtu
|
- | |
03 | 2.6121: Reduce hot water temperature to the minimum required | $1,753 | - | - |
$1,753
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,538 | $6,448 |
$21,538
118,699
kWh
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,180 | $96 |
$7,180
39,566
kWh
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $266 | $182 |
$266
1,465
kWh
|
- | - | |
07 | 3.6122: Install solid waste incinerator for heat | $55,176 | $50,000 | - |
$51,976
-
MMBtu
|
$3,200 | |
08 | 2.7221: Lower temperature during the winter season and vice-versa | $2,472 | - | - |
$2,472
-
MMBtu
|
- | |
09 | 2.2437: Recover waste heat from equipment | $738 | $2,000 | - |
$738
-
MMBtu
|
- | |
10 | 2.4227: Use compressor air filters | $479 | $120 |
$479
2,638
kWh
|
- | - | |
TOTAL RECOMMENDED | $99,058 | $85,371 |
$29,463
162,368
kWh
|
$66,395
-
MMBtu
|
$3,200 | ||
TOTAL IMPLEMENTED | $35,251 | $8,789 |
$29,197
160,903
kWh
|
$6,054
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs