ITAC Assessment: ST0023
ITAC logo
ITAC Assessment: ST0023
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product CAMERA,TAPE,& AUDIO CASE
NAICS
n/a
SIC 3161: Luggage
Sales Range $10
M
to 50
M
# of Employees 316
Plant Area
n/a
Annual Production 4,000,000
pieces
Production Hrs. Annual 2,353
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $136,959 754,982
kWh
Natural Gas $122,495 18,717
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $99,058 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $35,251

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7229: Air condition only space necessary $1,091 $125 - $1,091
-
MMBtu
-
02 2.1123: Install automatic stack damper $8,365 $26,400 - $8,365
-
MMBtu
-
03 2.6121: Reduce hot water temperature to the minimum required $1,753 - - $1,753
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $21,538 $6,448 $21,538
118,699
kWh
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,180 $96 $7,180
39,566
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $266 $182 $266
1,465
kWh
- -
07 3.6122: Install solid waste incinerator for heat $55,176 $50,000 - $51,976
-
MMBtu
$3,200
08 2.7221: Lower temperature during the winter season and vice-versa $2,472 - - $2,472
-
MMBtu
-
09 2.2437: Recover waste heat from equipment $738 $2,000 - $738
-
MMBtu
-
10 2.4227: Use compressor air filters $479 $120 $479
2,638
kWh
- -
TOTAL RECOMMENDED $99,058 $85,371 $29,463
162,368
kWh
$66,395
-
MMBtu
$3,200
TOTAL IMPLEMENTED $35,251 $8,789 $29,197
160,903
kWh
$6,054
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs