Assessment Year | 2022 |
---|---|
Principal Product | Architectural hardware |
NAICS | 332510: Hardware Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 140 |
Plant Area |
86,000
ft2
|
Annual Production | 1,500,000
pieces
|
Production Hrs. Annual | 6,500
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $151,027 | 1,770,056 |
kWh
|
$0.085 | |
Natural Gas | $50,845 | 2,838 |
MMBtu
|
$17.91 | |
Waste Disposal Costs | |||||
Water Usage | $17,888 | 3,182 |
Tgal
|
$5.62 | |
TOTAL YEARLY COSTS | $219,760 | ||||
RECOMMENDED SAVINGS* | $121,506 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $518 | $105 |
$518
6,073
kWh
|
- | - | - | |
02 | 3.6114: Use precipitating agents in waste water treatment that produce the least quantity of waste | $1,422 | $4,000 | - | - |
$1,422
-
Tgal
|
- | |
03 | 3.8225: Replace hexavalent chromium solutions with trivalent solutions | $30,091 | $55,770 |
$30,091
352,681
kWh
|
- | - | - | |
04 | 2.4312: Improve lubrication practices | $27,999 | $8,008 | - | - | - |
$27,999
-
gal
|
|
05 | 2.2211: Use optimum temperature | $4,521 | $3,500 | - |
$4,521
-
MMBtu
|
- | - | |
06 | 2.6224: Schedule baking times of small and large components | $2,357 | - | - |
$2,357
-
MMBtu
|
- | - | |
07 | 2.1113: Reduce combustion air flow to optimum | $30,793 | $45,000 | - |
$30,793
-
MMBtu
|
- | - | |
08 | 2.1117: Relocate oven / furnace to more efficient location | $7,698 | $5,000 | - |
$7,698
-
MMBtu
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,158 | $12,694 |
$14,158
165,984
kWh
|
- | - | - | |
10 | 2.3137: Use power during off-peak periods | $1,949 | - |
$1,949
15,242
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $121,506 | $134,077 |
$46,716
539,980
kWh
|
$45,368
-
MMBtu
|
$1,422
-
Tgal
|
$27,999
-
gal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | Other Liquid (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs