ITAC Assessment: OR0249
ITAC logo
ITAC Assessment: OR0249
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Carbonated Beverages
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 50,000
ft2
Annual Production 450,000,000
lb
Production Hrs. Annual 6,018
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $184,155 5,053,634
kWh
Natural Gas $68,629 14,008
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,299 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,043

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings
01 3.1161: Eliminate/reduce an operation $4,425 $300 - - $4,425
-
gal
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $18,578 $4,500 $18,578
625,733
kWh
- - -
03 2.2437: Recover waste heat from equipment $12,318 $17,000 $(-2,080.0)
(-69,168)
kWh
$14,398
-
MMBtu
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,311 $138 $1,292
39,273
kWh
- - $19
05 2.4133: Use most efficient type of electric motors $3,043 $11,076 $3,043
84,115
kWh
- - -
06 2.3212: Optimize plant power factor $1,624 $5,100 $1,624
-
kWh
- - -
TOTAL RECOMMENDED $41,299 $38,114 $22,457
679,953
kWh
$14,398
-
MMBtu
$4,425
-
gal
$19
TOTAL IMPLEMENTED $3,043 $11,076 $3,043
84,115
kWh
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs