| Assessment Year | 2026 |
|---|---|
| Principal Product | Disposable medical equipment, capital and disposable medical devices, surgical robots |
| NAICS | 339112: Surgical and Medical Instrument Manufacturing |
| SIC | 3841: Surgical and Medical Instruments and Apparatus |
| Sales Range | $10 M to 50M |
| # of Employees | 62 |
| Plant Area |
76,000
ft2
|
| Annual Production | 200,000
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $151,393 | 871,242 |
kWh
|
$0.17 |
| Electricity Demand | $114,935 | 2,250 |
kW-mo/yr
|
$51.08 |
| Natural Gas | $35,236 | 1,675 |
MMBtu
|
$21.03 |
| TOTAL YEARLY COSTS | $301,564 | |||
| RECOMMENDED SAVINGS* | $45,852 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $420 | $619 |
$156
896
kWh
|
$264
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $646 | - |
$493
2,835
kWh
|
$153
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,556 | $5,088 |
$234
1,345
kWh
|
$1,322
-
kW-mo/yr
|
- | |
| 04 | 2.7221: Lower temperature during the winter season and vice-versa | $16,918 | - |
$2,049
11,775
kWh
|
- |
$14,869
-
MMBtu
|
|
| 05 | 2.9114: Use solar heat to make electricty | $26,312 | $348,375 |
$26,312
151,216
kWh
|
- | - | |
| TOTAL RECOMMENDED | $45,852 | $354,082 |
$29,244
168,067
kWh
|
$1,739
-
kW-mo/yr
|
$14,869
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs