Assessment Year | 2006 |
---|---|
Principal Product | Concrete pipe |
NAICS | 327332: Concrete Pipe Manufacturing |
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
104,000
ft2
|
Annual Production | 230,000
ton
|
Production Hrs. Annual | 3,146
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $89,228 | 2,602,575 |
kWh
|
$0.034 |
Electricity Demand | $118,268 | 8,930 |
kW-mo/yr
|
$13.24 |
Electricity Fees | $2,096 | - |
|
- |
Natural Gas | $162,918 | 18,021 |
MMBtu
|
$9.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,404 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,124 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $4,250 | $4,140 | - | - |
$4,250
-
MMBtu
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,000 | $270 |
$1,120
36,800
kWh
|
$2,880
-
kW-mo/yr
|
- | - | - | |
03 | 2.2135: Repair and eliminate steam leaks | $3,370 | $650 | - | - |
$3,370
-
MMBtu
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $400 | $400 |
$150
4,800
kWh
|
$250
-
kW-mo/yr
|
- | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $54 | $171 |
$21
688
kWh
|
$33
-
kW-mo/yr
|
- | - | - | |
06 | 2.7232: Replace existing hvac unit with high efficiency model | $5,370 | $4,040 | - | - |
$5,370
-
MMBtu
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,050 | $14,465 |
$2,330
76,700
kWh
|
$2,480
-
kW-mo/yr
|
- | $140 | $100 | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,700 | $3,100 |
$640
20,900
kWh
|
$1,010
-
kW-mo/yr
|
- | $30 | $20 | |
09 | 2.9114: Use solar heat to make electricty | $1,210 | $2,950 |
$430
14,100
kWh
|
$780
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $25,404 | $30,186 |
$4,691
153,988
kWh
|
$7,433
-
kW-mo/yr
|
$12,990
-
MMBtu
|
$170 | $120 | ||
TOTAL IMPLEMENTED | $17,124 | $20,096 |
$3,621
118,988
kWh
|
$5,643
-
kW-mo/yr
|
$7,620
-
MMBtu
|
$140 | $100 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs