ITAC Assessment: CO0587
ITAC logo
ITAC Assessment: CO0587
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Concrete pipe
NAICS 327332: Concrete Pipe Manufacturing
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 104,000
ft2
Annual Production 230,000
ton
Production Hrs. Annual 3,146
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $89,228 2,602,575
kWh
Electricity Demand $118,268 8,930
kW-mo/yr
Electricity Fees $2,096 -
Natural Gas $162,918 18,021
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,404 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,124

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2136: Install / repair insulation on steam lines $4,250 $4,140 - - $4,250
-
MMBtu
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,000 $270 $1,120
36,800
kWh
$2,880
-
kW-mo/yr
- - -
03 2.2135: Repair and eliminate steam leaks $3,370 $650 - - $3,370
-
MMBtu
- -
04 2.4221: Install compressor air intakes in coolest locations $400 $400 $150
4,800
kWh
$250
-
kW-mo/yr
- - -
05 2.4133: Use most efficient type of electric motors $54 $171 $21
688
kWh
$33
-
kW-mo/yr
- - -
06 2.7232: Replace existing hvac unit with high efficiency model $5,370 $4,040 - - $5,370
-
MMBtu
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $5,050 $14,465 $2,330
76,700
kWh
$2,480
-
kW-mo/yr
- $140 $100
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,700 $3,100 $640
20,900
kWh
$1,010
-
kW-mo/yr
- $30 $20
09 2.9114: Use solar heat to make electricty $1,210 $2,950 $430
14,100
kWh
$780
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $25,404 $30,186 $4,691
153,988
kWh
$7,433
-
kW-mo/yr
$12,990
-
MMBtu
$170 $120
TOTAL IMPLEMENTED $17,124 $20,096 $3,621
118,988
kWh
$5,643
-
kW-mo/yr
$7,620
-
MMBtu
$140 $100
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs