ITAC Assessment: SD0399
ITAC logo
ITAC Assessment: SD0399
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Stone countertops and interiors
NAICS 327991: Cut Stone and Stone Product Manufacturing
SIC 3281: Cut Stone and Stone Products
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 20,000
ft2
Annual Production 12,500
pieces
Production Hrs. Annual 4,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $34,970 414,322
kWh
Electricity Demand $10,305 811
kW-mo/yr
Electricity Fees $29,970 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,476 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,537

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,380 $6,025 $1,436
17,017
kWh
$944
-
kW-mo/yr
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,267 $6,700 $2,267
26,856
kWh
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,543 $4,247 $1,543
18,277
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,157 $5,934 $797
9,440
kWh
$360
-
kW-mo/yr
05 2.7224: Reduce space conditioning during non-working hours $1,129 - $1,129
13,381
kWh
-
TOTAL RECOMMENDED $8,476 $22,906 $7,172
84,971
kWh
$1,304
-
kW-mo/yr
TOTAL IMPLEMENTED $3,537 $11,959 $2,233
26,457
kWh
$1,304
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs