ITAC Assessment: AM0334
ITAC logo
ITAC Assessment: AM0334
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Leveling of steel coils
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $50
M
to 100
M
# of Employees 100
Plant Area 250,000
ft2
Annual Production 120,000
ton
Production Hrs. Annual 3,654
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $98,773 1,532,239
kWh
Electricity Demand $23,734 7,776
kW-mo/yr
Natural Gas $11,557 7,105
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,405 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,560

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.3212: Optimize plant power factor $18,200 $22,300 - $18,200
-
kW-mo/yr
- - - -
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $11,680 $40,600 $11,680
216,295
kWh
- - - - -
03 2.6218: Turn off equipment when not in use $4,900 - - - $4,900
-
MMBtu
- - -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,000 - - $4,000
-
kW-mo/yr
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,300 $1,000 $2,300
43,376
kWh
- - - - -
06 2.7124: Make a practice of turning off lights when not needed $2,070 $35 $1,560
29,308
kWh
$510
-
kW-mo/yr
- - - -
07 3.8211: Convert to aqueous cleaning system $1,260 $1,030 - - - $1,260
-
gal
- -
08 4.652: Replace existing equipment with more suitable substitutes $165 $340 $145
2,638
kWh
$20
-
kW-mo/yr
- - - -
09 3.7131: Use a rag recycle service $310 - - - - - $310
-
lb
-
10 4.821: Pay bills on time to avoid late fees $300 - - - - - - $300
11 2.6212: Turn off equipment during breaks, reduce operating time $220 - $220
4,103
kWh
- - - - -
TOTAL RECOMMENDED $45,405 $65,305 $15,905
295,720
kWh
$22,730
-
kW-mo/yr
$4,900
-
MMBtu
$1,260
-
gal
$310
-
lb
$300
TOTAL IMPLEMENTED $29,560 $24,365 $4,080
76,787
kWh
$18,710
-
kW-mo/yr
$4,900
-
MMBtu
$1,260
-
gal
$310
-
lb
$300
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs