Assessment Year | 2023 |
---|---|
Principal Product | Cable assemblies |
NAICS | 335929: Other Communication and Energy Wire Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
55,000
ft2
|
Annual Production | 500,000
units
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $126,817 | 561,767 |
kWh
|
$0.23 |
Electricity Demand | $25,284 | 1,616 |
kW-mo/yr
|
$15.65 |
Natural Gas | $6,753 | 284 |
MMBtu
|
$23.77 |
TOTAL YEARLY COSTS | $158,854 | |||
RECOMMENDED SAVINGS* | $104,054 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,431 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $72,623 | $275,269 |
$68,798
304,759
kWh
|
$3,825
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,741 | $652 |
$1,480
6,538
kWh
|
$261
-
kW-mo/yr
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $424 | $194 |
$388
1,704
kWh
|
$36
-
kW-mo/yr
|
- | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $1,185 | - | - | - |
$1,185
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $22,309 | $22,700 |
$18,264
80,867
kWh
|
$4,045
-
kW-mo/yr
|
- | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $5,772 | - |
$5,772
25,317
kWh
|
- | - | |
TOTAL RECOMMENDED | $104,054 | $298,815 |
$94,702
419,185
kWh
|
$8,167
-
kW-mo/yr
|
$1,185
-
MMBtu
|
||
TOTAL IMPLEMENTED | $31,431 | $23,546 |
$25,904
114,426
kWh
|
$4,342
-
kW-mo/yr
|
$1,185
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs