| Assessment Year | 2025 |
|---|---|
| Principal Product | Wine |
| NAICS | 312130: Wineries |
| SIC | 2084: Wines, Brandy, and Brandy Spirits |
| Sales Range | $100 M to 500M |
| # of Employees | 90 |
| Plant Area |
518,000
ft2
|
| Annual Production | 50,000
ton
|
| Production Hrs. Annual | 1,536
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $766,396 | 4,350,931 |
kWh
|
$0.18 |
| Electricity Demand | $145,845 | 7,821 |
kW-mo/yr
|
$18.65 |
| Natural Gas | $284,542 | 17,123 |
MMBtu
|
$16.62 |
| TOTAL YEARLY COSTS | $1,196,783 | |||
| RECOMMENDED SAVINGS* | $89,855 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,844 | - |
$19,044
108,135
kWh
|
- | - | $(-1,200.0) | |
| 02 | 2.7224: Reduce space conditioning during non-working hours | $16,164 | $441 |
$7,355
41,765
kWh
|
- |
$8,809
-
MMBtu
|
- | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $768 | $122 |
$671
3,810
kWh
|
$97
-
kW-mo/yr
|
- | - | |
| 04 | 2.2511: Insulate bare equipment | $523 | $419 | - | - |
$523
-
MMBtu
|
- | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,321 | $6,254 |
$7,321
41,572
kWh
|
- | - | - | |
| 06 | 2.4226: Use / purchase optimum sized compressor | $42,980 | $125,625 |
$37,424
222,515
kWh
|
$5,556
-
kW-mo/yr
|
- | - | |
| 07 | 2.2437: Recover waste heat from equipment | $4,255 | $13,190 | - | - |
$4,255
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $89,855 | $146,051 |
$71,815
417,797
kWh
|
$5,653
-
kW-mo/yr
|
$13,587
-
MMBtu
|
$(-1,200.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs