Assessment Year | 2024 |
---|---|
Principal Product | Chocolate and panned candy |
NAICS | 311352: Confectionery Manufacturing from Purchased Chocolate |
SIC | 2067: Chewing Gum |
Sales Range | $100 M to 500M |
# of Employees | 218 |
Plant Area |
300,000
ft2
|
Annual Production | 26,000,000
lb
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $826,335 | 10,744,271 |
kWh
|
$0.077 | |
Electricity Demand | $383,356 | 19,998 |
kW-mo/yr
|
$19.17 | |
Natural Gas | $568,492 | 44,240 |
MMBtu
|
$12.85 | |
Waste Disposal Costs | |||||
Water Disposal | $132,453 | 17,932 |
Tgal
|
$7.39 | |
TOTAL YEARLY COSTS | $1,910,636 | ||||
RECOMMENDED SAVINGS* | $424,228 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,669 | - |
$3,869
50,296
kWh
|
- | - | - | $(-1,200.0) | - | |
02 | 2.7224: Reduce space conditioning during non-working hours | $8,680 | $588 |
$2,692
35,002
kWh
|
- |
$5,988
-
MMBtu
|
- | - | - | |
03 | 2.2135: Repair and eliminate steam leaks | $8,671 | $516 | - | - |
$5,741
-
MMBtu
|
$2,930
-
Tgal
|
- | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $5,071 | $854 |
$5,071
65,941
kWh
|
- | - | - | - | - | |
05 | 2.2121: Increase amount of condensate returned | $26,010 | $8,735 | - | - |
$17,219
-
MMBtu
|
$8,791
-
Tgal
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,576 | $3,859 |
$6,251
81,294
kWh
|
$2,325
-
kW-mo/yr
|
- | - | $4,047 | $(-47.0) | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,943 | $10,277 |
$11,943
155,311
kWh
|
- | - | - | - | - | |
08 | 2.2628: Utilize a less expensive cooling method | $155,547 | $160,389 |
$149,934
1,949,730
kWh
|
$5,613
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.6231: Utilize controls to operate equipment only when needed | $14,307 | $15,295 |
$14,307
186,053
kWh
|
- | - | - | - | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,369 | $7,928 |
$1,369
17,802
kWh
|
- | - | - | - | - | |
11 | 2.9114: Use solar heat to make electricty | $177,385 | $2,104,448 |
$177,385
2,306,694
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $424,228 | $2,312,889 |
$372,821
4,848,123
kWh
|
$7,938
-
kW-mo/yr
|
$28,948
-
MMBtu
|
$11,721
-
Tgal
|
$2,847 | $(-47.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs