| Assessment Year | 2024 |
|---|---|
| Principal Product | Synthetic Peptides |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $10 M to 50M |
| # of Employees | 30 |
| Plant Area |
50,000
ft2
|
| Annual Production | 12,000,000
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $102,319 | 659,977 |
kWh
|
$0.16 |
| Electricity Demand | $51,128 | 1,399 |
kW-mo/yr
|
$36.55 |
| Natural Gas | $32,672 | 1,670 |
MMBtu
|
$19.56 |
| TOTAL YEARLY COSTS | $186,119 | |||
| RECOMMENDED SAVINGS* | $16,345 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,345 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $4,288 | - |
$4,288
27,660
kWh
|
- | - | - | - | |
| 02 | 2.7314: Reduce ventilation air | $4,851 | - |
$2,268
14,632
kWh
|
- |
$2,583
-
MMBtu
|
- | - | |
| 03 | 2.6231: Utilize controls to operate equipment only when needed | $2,887 | $1,146 |
$2,887
18,623
kWh
|
- | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,599 | $3,962 |
$1,292
8,332
kWh
|
$1,205
-
kW-mo/yr
|
- | $110 | $(-7.9) | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,720 | $4,257 |
$1,720
11,097
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $16,345 | $9,365 |
$12,455
80,344
kWh
|
$1,205
-
kW-mo/yr
|
$2,583
-
MMBtu
|
$110 | $(-7.9) | ||
| TOTAL IMPLEMENTED | $16,345 | $9,365 |
$12,455
80,344
kWh
|
$1,205
-
kW-mo/yr
|
$2,583
-
MMBtu
|
$110 | $(-7.9) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs