Assessment Year | 2024 |
---|---|
Principal Product | Coated metal sheets |
NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 57 |
Plant Area |
144,000
ft2
|
Annual Production | 55,000
ton
|
Production Hrs. Annual | 6,912
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $583,608 | 3,347,181 |
kWh
|
$0.17 |
Electricity Demand | $298,964 | 6,744 |
kW-mo/yr
|
$44.33 |
Electricity Fees | $14,410 | - |
|
- |
Natural Gas | $1,398,820 | 132,264 |
MMBtu
|
$10.58 |
TOTAL YEARLY COSTS | $2,295,802 | |||
RECOMMENDED SAVINGS* | $1,332,876 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,186 | - |
$17,086
97,970
kWh
|
- | - | $(-900.0) | |
02 | 2.4235: Remove or close off unneeded compressed air lines | $6,885 | $3,504 |
$6,885
39,481
kWh
|
- | - | - | |
03 | 2.2443: Re-use or recycle hot or cold process exhaust air | $99,094 | $49,118 | - | - |
$99,094
-
MMBtu
|
- | |
04 | 2.2442: Preheat combustion air with waste heat | $614,286 | $1,532,000 | - | - |
$614,286
-
MMBtu
|
- | |
05 | 2.4226: Use / purchase optimum sized compressor | $44,171 | $125,600 |
$30,074
172,440
kWh
|
$14,097
-
kW-mo/yr
|
- | - | |
06 | 2.9114: Use solar heat to make electricty | $552,254 | $2,633,668 |
$552,254
3,166,592
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $1,332,876 | $4,343,890 |
$606,299
3,476,483
kWh
|
$14,097
-
kW-mo/yr
|
$713,380
-
MMBtu
|
$(-900.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs