ITAC Assessment: SF0609
ITAC logo
ITAC Assessment: SF0609
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Red wine, white wine, sparkling wine base
NAICS 312130: Wineries
SIC 2084: Wines, Brandy, and Brandy Spirits
Sales Range $50
M
to 100
M
# of Employees 56
Plant Area 350,000
ft2
Annual Production 2,960
Tgal
Production Hrs. Annual 2,784
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $412,034 1,422,792
kWh
Natural Gas $240,385 13,878
MMBtu
TOTAL YEARLY COSTS $652,419
RECOMMENDED SAVINGS* $554,106 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $116,084

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
01 2.7224: Reduce space conditioning during non-working hours $12,048 $1,594 $12,048
41,660
kWh
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,389 $1,640 $14,229
49,135
kWh
- - $(-3,840.0)
03 2.2515: Use optimum thickness insulation $1,473 $338 - - $1,473
-
MMBtu
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,090 $2,155 $3,090
10,672
kWh
- - -
05 2.6231: Utilize controls to operate equipment only when needed $32,617 $36,367 $32,617
112,628
kWh
- - -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $56,467 $66,447 $56,467
194,894
kWh
- - -
07 2.2515: Use optimum thickness insulation $8,652 $21,442 $8,652
29,876
kWh
- - -
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,153 $9,827 $3,153
10,888
kWh
- - -
09 2.9121: Install wind powered electric generator $426,217 $1,338,900 $474,069
1,636,980
kWh
$(-40,000.0) - $(-7,852.0)
TOTAL RECOMMENDED $554,106 $1,478,710 $604,325
2,086,733
kWh
$(-40,000.0) $1,473
-
MMBtu
$(-11,692.0)
TOTAL IMPLEMENTED $116,084 $108,541 $118,451
408,989
kWh
- $1,473
-
MMBtu
$(-3,840.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs