| Assessment Year | 1987 |
|---|---|
| Principal Product | REFURBISHED RAIL CARS |
| NAICS |
n/a
|
| SIC | 3743: Railroad Equipment |
| Sales Range | $1 M to 5M |
| # of Employees | 44 |
| Plant Area |
n/a
|
| Annual Production | 1,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $148,829 | 2,325,909 |
kWh
|
$0.064 |
| Natural Gas | $42,314 | 11,067 |
MMBtu
|
$3.82 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,231 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,397 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,397 | - |
$2,517
39,273
kWh
|
- | $(-120.0) | |
| 02 | 2.7261: Install timers and/or thermostats | $16,197 | $1,400 | - |
$16,197
-
MMBtu
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $637 | $668 |
$612
9,672
kWh
|
- | $25 | |
| TOTAL RECOMMENDED | $19,231 | $2,068 |
$3,129
48,945
kWh
|
$16,197
-
MMBtu
|
$(-95.0) | ||
| TOTAL IMPLEMENTED | $2,397 | - |
$2,517
39,273
kWh
|
- | $(-120.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs