| Assessment Year | 2023 |
|---|---|
| Principal Product | Chili, Garlic and Onion Powder |
| NAICS | 311999: All Other Miscellaneous Food Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 250 |
| Plant Area |
500,000
ft2
|
| Annual Production | 12,500,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $844,553 | 7,071,893 |
kWh
|
$0.12 |
| Electricity Demand | $185,985 | 15,816 |
kW-mo/yr
|
$11.76 |
| Natural Gas | $78,410 | 6,170 |
MMBtu
|
$12.71 |
| TOTAL YEARLY COSTS | $1,108,948 | |||
| RECOMMENDED SAVINGS* | $145,997 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $10,580 | - | - |
$10,580
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $10,143 | - |
$10,143
84,946
kWh
|
- | - | - | - | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $38,807 | $8,920 |
$12,759
106,862
kWh
|
- |
$26,048
-
MMBtu
|
- | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $54,583 | $28,593 |
$45,898
384,410
kWh
|
$8,685
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $7,223 | $4,344 |
$5,955
49,875
kWh
|
$1,268
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,717 | $13,055 |
$14,381
120,447
kWh
|
$4,086
-
kW-mo/yr
|
- | $393 | $(-143.0) | |
| 07 | 2.2437: Recover waste heat from equipment | $5,385 | $9,100 | - | - |
$5,385
-
MMBtu
|
- | - | |
| 08 | 2.2511: Insulate bare equipment | $559 | $1,938 | - | - |
$559
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $145,997 | $65,950 |
$89,136
746,540
kWh
|
$24,619
-
kW-mo/yr
|
$31,992
-
MMBtu
|
$393 | $(-143.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs