Assessment Year | 1998 |
---|---|
Principal Product | injection molded plastic parts |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 80 |
Plant Area |
22,000
ft2
|
Annual Production | 50,000,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,487 | 1,033,705 |
kWh
|
$0.051 |
Electricity Demand | $10,811 | 2,765 |
kW-mo/yr
|
$3.91 |
Electricity Fees | $12,541 | - |
|
- |
Natural Gas | $1,550 | 248 |
MMBtu
|
$6.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,391 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,526 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $3,125 | - | - |
$2,101
-
kW-mo/yr
|
$1,024 | - | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $562 | $99 |
$280
5,862
kWh
|
$21
-
kW-mo/yr
|
$261 | - | - | - | - | |
03 | 2.4314: Use synthetic lubricant | $641 | $94 |
$315
8,206
kWh
|
$29
-
kW-mo/yr
|
$297 | - | - | - | - | |
04 | 2.7134: Use photocell controls | $357 | $116 |
$188
3,810
kWh
|
- | $169 | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,881 | $3,488 |
$1,907
39,859
kWh
|
$179
-
kW-mo/yr
|
$1,795 | - | - | - | - | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $9,366 | $6,500 | - | - | - |
$4,866
-
lb
|
- | - | $4,500 | |
07 | 4.515: Install shelves / racks to utilize unused space | $13,832 | $1,662 | - | - | - | - | - | $13,832 | - | |
08 | 4.423: Move product using mechanical means | $29,627 | $13,923 |
$(-196.0)
(-4,103)
kWh
|
$(-166.0)
-
kW-mo/yr
|
$(-251.0) | - | $30,240 | - | - | |
TOTAL RECOMMENDED | $61,391 | $25,882 |
$2,494
53,634
kWh
|
$2,164
-
kW-mo/yr
|
$3,295 |
$4,866
-
lb
|
$30,240 | $13,832 | $4,500 | ||
TOTAL IMPLEMENTED | $27,526 | $8,355 |
$595
14,068
kWh
|
$2,151
-
kW-mo/yr
|
$1,582 |
$4,866
-
lb
|
- | $13,832 | $4,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs