Assessment Year | 2022 |
---|---|
Principal Product | Waste water |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $1 M to 5M |
# of Employees | 10 |
Plant Area |
770,000
ft2
|
Annual Production | 421,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $215,552 | 1,335,718 |
kWh
|
$0.16 |
Electricity Demand | $90,955 | 2,388 |
kW-mo/yr
|
$38.09 |
Electricity Fees | $309,091 | - |
|
- |
TOTAL YEARLY COSTS | $615,598 | |||
RECOMMENDED SAVINGS* | $242,960 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $72,699 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $14,854 | - |
$14,854
92,033
kWh
|
- | - | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $53,458 | $172,352 |
$40,398
250,397
kWh
|
$13,060
-
kW-mo/yr
|
- | - | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $20,922 | $73,113 |
$20,922
129,629
kWh
|
- | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,794 | $15,591 |
$3,794
23,505
kWh
|
- | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,635 | $18,061 |
$2,721
16,858
kWh
|
$914
-
kW-mo/yr
|
- | - | |
06 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $95,881 | $341,026 |
$122,707
760,266
kWh
|
$39,800
-
kW-mo/yr
|
$(-52,713.0)
-
MMBtu
|
$(-13,913.0) | |
07 | 2.9114: Use solar heat to make electricty | $50,416 | $292,043 |
$50,416
312,365
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $242,960 | $912,186 |
$255,812
1,585,053
kWh
|
$53,774
-
kW-mo/yr
|
$(-52,713.0)
-
MMBtu
|
$(-13,913.0) | ||
TOTAL IMPLEMENTED | $72,699 | $325,695 |
$71,785
444,761
kWh
|
$914
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs