Assessment Year | 2022 |
---|---|
Principal Product | Metal Cans |
NAICS | 332431: Metal Can Manufacturing |
SIC | 3411: Metal Cans |
Sales Range | $100 M to 500M |
# of Employees | 87 |
Plant Area |
145,000
ft2
|
Annual Production | 275,000,000
units
|
Production Hrs. Annual | 5,280
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $320,696 | 3,629,648 |
kWh
|
$0.088 | |
Electricity Demand | $135,760 | 8,292 |
kW-mo/yr
|
$16.37 | |
Natural Gas | $67,177 | 10,219 |
MMBtu
|
$6.57 | |
Waste Disposal Costs | |||||
Water Usage | $3,300 | 1,251 |
Tgal
|
$2.64 | |
Water Disposal | $5,992 | 1,251 |
Tgal
|
$4.79 | |
TOTAL YEARLY COSTS | $532,925 | ||||
RECOMMENDED SAVINGS* | $94,329 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $83,981 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $3,573 | $100 |
$2,510
28,556
kWh
|
$1,063
-
kW-mo/yr
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,525 | - |
$9,325
106,095
kWh
|
- | - | $(-800.0) | - | |
03 | 2.6218: Turn off equipment when not in use | $37,544 | - |
$37,544
427,172
kWh
|
- | - | - | - | |
04 | 2.7224: Reduce space conditioning during non-working hours | $2,201 | $1,018 |
$1,305
14,852
kWh
|
- |
$896
-
MMBtu
|
- | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $13,523 | $11,498 |
$13,523
153,857
kWh
|
- | - | - | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $6,583 | $6,929 |
$6,583
74,902
kWh
|
- | - | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,775 | $8,827 |
$6,775
77,087
kWh
|
- | - | - | - | |
08 | 2.6231: Utilize controls to operate equipment only when needed | $1,024 | $2,236 |
$1,024
11,648
kWh
|
- | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,144 | $23,308 |
$7,198
81,895
kWh
|
$3,164
-
kW-mo/yr
|
- | - | $(-218.0) | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,437 | $13,019 |
$3,033
34,506
kWh
|
$1,404
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $94,329 | $66,935 |
$88,820
1,010,570
kWh
|
$5,631
-
kW-mo/yr
|
$896
-
MMBtu
|
$(-800.0) | $(-218.0) | ||
TOTAL IMPLEMENTED | $83,981 | $58,008 |
$79,535
904,927
kWh
|
$4,568
-
kW-mo/yr
|
$896
-
MMBtu
|
$(-800.0) | $(-218.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs