Assessment Year | 1991 |
---|---|
Principal Product | SANDERS & GRINDERS |
NAICS |
n/a
|
SIC | 3546: Power-Driven Handtools |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 200
pieces
|
Production Hrs. Annual | 4,032
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $64,235 | 1,175,850 |
kWh
|
$0.055 |
Natural Gas | $13,869 | 3,175 |
MMBtu
|
$4.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,675 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,675 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $4,004 | $700 |
$2,562
46,893
kWh
|
$1,442
-
MMBtu
|
- | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $1,315 | $1,860 | - |
$1,315
-
MMBtu
|
- | |
03 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,071 | - |
$720
13,189
kWh
|
- | $351 | |
04 | 2.2692: Use outside cold water source as a supply of cooling water | $1,066 | $525 |
$192
3,517
kWh
|
$874
-
MMBtu
|
- | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $577 | $350 |
$96
1,758
kWh
|
$481
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $83 | $119 |
$83
1,465
kWh
|
- | - | |
07 | 2.7224: Reduce space conditioning during non-working hours | $415 | - | - |
$415
-
MMBtu
|
- | |
08 | 2.6218: Turn off equipment when not in use | $144 | - |
$144
7,620
kWh
|
- | - | |
TOTAL RECOMMENDED | $8,675 | $3,554 |
$3,797
74,442
kWh
|
$4,527
-
MMBtu
|
$351 | ||
TOTAL IMPLEMENTED | $8,675 | $3,554 |
$3,797
74,442
kWh
|
$4,527
-
MMBtu
|
$351 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs