| Assessment Year | 1990 |
|---|---|
| Principal Product | ALUMINUM ALLOY INGOTS |
| NAICS |
n/a
|
| SIC | 3363: Aluminum Die-Castings |
| Sales Range | $50 M to 100M |
| # of Employees | 70 |
| Plant Area |
n/a
|
| Annual Production | 63,000
ton
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $286,253 | 4,307,151 |
kWh
|
$0.066 |
| Natural Gas | $553,520 | 132,569 |
MMBtu
|
$4.18 |
| LPG | $25,605 | 5,968 |
MMBtu
|
$4.29 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $85,506 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $68,217 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2424: Use heat in flue gases to preheat products or materials | $68,217 | $70,000 |
$68,217
-
MMBtu
|
- | |
| 02 | 2.3133: Consider three or four days around-the-clock operation rather than one or two shifts per day | $12,691 | - |
$20,691
-
MMBtu
|
$(-8,000.0) | |
| 03 | 2.2515: Use optimum thickness insulation | $4,598 | $3,900 |
$4,598
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $85,506 | $73,900 |
$93,506
-
MMBtu
|
$(-8,000.0) | ||
| TOTAL IMPLEMENTED | $68,217 | $70,000 |
$68,217
-
MMBtu
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs