| Assessment Year | 2021 |
|---|---|
| Principal Product | Metal Containers |
| NAICS | 332439: Other Metal Container Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $5 M to 10M |
| # of Employees | 50 |
| Plant Area |
270,000
ft2
|
| Annual Production | 2,400
units
|
| Production Hrs. Annual | 2,525
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $86,270 | 399,236 |
kWh
|
$0.22 | |
| Electricity Demand | $15,185 | 1,154 |
kW-mo/yr
|
$13.16 | |
| Electricity Fees | $8,724 | - |
|
- | |
| Natural Gas | $812 | 48 |
MMBtu
|
$17.09 | |
| LPG | $11,811 | 475 |
MMBtu
|
$24.88 | |
| Waste Disposal Costs | |||||
| Water Usage | $7,023 | 2,315 |
Tgal
|
$3.03 | |
| Water Disposal | $6,356 | 2,118 |
Tgal
|
$3.00 | |
| Other Liquid (non-haz) | $2,323 | 207,015 |
gal
|
$0.011 | |
| TOTAL YEARLY COSTS | $138,504 | ||||
| RECOMMENDED SAVINGS* | $96,257 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $96,257 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,483 | - |
$4,100
18,359
kWh
|
$1,133
-
kW-mo/yr
|
$(-1,750.0) | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $141 | $62 |
$124
504
kWh
|
$17
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,636 | $26,920 |
$7,340
32,870
kWh
|
$3,150
-
kW-mo/yr
|
$338 | $(-192.0) | |
| 04 | 2.4224: Upgrade controls on compressors | $4,632 | $30,160 |
$3,629
16,252
kWh
|
$1,003
-
kW-mo/yr
|
- | - | |
| 05 | 2.9114: Use solar heat to make electricty | $77,365 | $283,655 |
$77,365
346,458
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $96,257 | $340,797 |
$92,558
414,443
kWh
|
$5,303
-
kW-mo/yr
|
$(-1,412.0) | $(-192.0) | ||
| TOTAL IMPLEMENTED | $96,257 | $340,797 |
$92,558
414,443
kWh
|
$5,303
-
kW-mo/yr
|
$(-1,412.0) | $(-192.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs