Assessment Year | 1997 |
---|---|
Principal Product | Steel bases and buildings |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
101,000
ft2
|
Annual Production | 8,500
ton
|
Production Hrs. Annual | 5,406
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $112,347 | 1,922,040 |
kWh
|
$0.058 |
Electricity Demand | $44,513 | 5,331 |
kW-mo/yr
|
$8.35 |
Natural Gas | $46,830 | 9,695 |
MMBtu
|
$4.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,497 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,347 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Gaseous Waste Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $5,285 | $2,390 |
$3,949
67,409
kWh
|
$1,336
-
kW-mo/yr
|
- | - | - | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $698 | $600 |
$421
12,016
kWh
|
$277
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $580 | $100 |
$580
9,965
kWh
|
- | - | - | - | |
04 | 3.7313: Eliminate oxygen loss | $479 | $20 | - | - | - |
$479
-
lb
|
- | |
05 | 2.7135: Install occupancy sensors | $452 | $400 |
$273
7,620
kWh
|
$179
-
kW-mo/yr
|
- | - | - | |
06 | 2.7495: Install replacement doors | $355 | $1,050 | - | - |
$355
-
MMBtu
|
- | - | |
07 | 4.821: Pay bills on time to avoid late fees | $325 | - | - | - | - | - | $325 | |
08 | 2.7444: Close holes and openings in building such as broken windows | $303 | $335 | - | - |
$303
-
MMBtu
|
- | - | |
09 | 2.6218: Turn off equipment when not in use | $20 | - |
$12
293
kWh
|
$8
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $8,497 | $4,895 |
$5,235
97,303
kWh
|
$1,800
-
kW-mo/yr
|
$658
-
MMBtu
|
$479
-
lb
|
$325 | ||
TOTAL IMPLEMENTED | $7,347 | $3,895 |
$4,541
77,667
kWh
|
$1,344
-
kW-mo/yr
|
$658
-
MMBtu
|
$479
-
lb
|
$325 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Gaseous Waste Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs