ITAC Assessment: SF0569
ITAC logo
ITAC Assessment: SF0569
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Still Wines
NAICS 312130: Wineries
SIC 2084: Wines, Brandy, and Brandy Spirits
Sales Range $1
M
to 5
M
# of Employees 16
Plant Area 67,500
ft2
Annual Production 67
Tgal
Production Hrs. Annual 3,200
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $153,292 978,433
kWh
Electricity Demand $24,220 2,151
kW-mo/yr
Electricity Fees $32,933 -
LPG $34,503 2,631
MMBtu
TOTAL YEARLY COSTS $244,948
RECOMMENDED SAVINGS* $277,371 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $277,371

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Primary Product Savings
01 2.2625: Chill water to the highest temperature possible $5,931 - $5,931
35,285
kWh
- -
02 2.7261: Install timers and/or thermostats $4,698 $3,740 $4,698
27,945
kWh
- -
03 2.2691: Shut off cooling if cold outside air will cool process $5,693 $9,138 $5,693
33,866
kWh
- -
04 2.2621: Modify refrigeration system to operate at a lower pressure $7,674 $23,650 $7,674
45,651
kWh
- -
05 2.7135: Install occupancy sensors $2,279 $6,956 $2,279
13,559
kWh
- -
06 2.9114: Use solar heat to make electricty $107,546 $722,227 $104,851
832,207
kWh
$2,695
-
kW-mo/yr
-
07 3.1191: Change procedures / equipment / operating conditions $143,550 $77,720 - - $143,550
TOTAL RECOMMENDED $277,371 $843,431 $131,126
988,513
kWh
$2,695
-
kW-mo/yr
$143,550
TOTAL IMPLEMENTED $277,371 $843,431 $131,126
988,513
kWh
$2,695
-
kW-mo/yr
$143,550
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs