Assessment Year | 2020 |
---|---|
Principal Product | in shell walnuts, shelled walnuts |
NAICS | 311911: Roasted Nuts and Peanut Butter Manufacturing |
SIC | 2068: Salted and Roasted Nuts and Seeds |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
35,000
ft2
|
Annual Production | 9,620
ton
|
Production Hrs. Annual | 3,848
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $62,948 | 515,921 |
kWh
|
$0.12 | |
Electricity Demand | $34,022 | 1,667 |
kW-mo/yr
|
$20.41 | |
Waste Disposal Costs | |||||
Water Usage | $10,000 | 500 |
Tgal
|
$20.00 | |
TOTAL YEARLY COSTS | $106,970 | ||||
RECOMMENDED SAVINGS* | $94,426 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $92,176 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,802 | - |
$2,342
19,192
kWh
|
- | $(-540.0) | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $4,683 | $575 |
$4,683
38,385
kWh
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $959 | $60 |
$780
6,397
kWh
|
$179
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,769 | $2,289 |
$10,769
65,788
kWh
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,729 | $864 |
$1,729
14,169
kWh
|
- | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,238 | $5,536 |
$4,113
33,754
kWh
|
$1,125
-
kW-mo/yr
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,455 | $3,366 |
$1,928
15,801
kWh
|
$527
-
kW-mo/yr
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,676 | $16,092 |
$4,924
40,354
kWh
|
$1,462
-
kW-mo/yr
|
$164 | $126 | |
09 | 2.9114: Use solar heat to make electricty | $57,865 | $348,493 |
$51,859
425,041
kWh
|
$6,006
-
kW-mo/yr
|
- | - | |
10 | 2.3132: Recharge batteries on during off-peak demand periods | $2,250 | $1,064 | - |
$2,250
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $94,426 | $378,339 |
$83,127
658,881
kWh
|
$11,549
-
kW-mo/yr
|
$(-376.0) | $126 | ||
TOTAL IMPLEMENTED | $92,176 | $377,275 |
$83,127
658,881
kWh
|
$9,299
-
kW-mo/yr
|
$(-376.0) | $126 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs