Assessment Year | 2020 |
---|---|
Principal Product | Specialty Food Products |
NAICS | 311999: All Other Miscellaneous Food Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
24,498
ft2
|
Annual Production | 200,000
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $197,315 | 1,122,123 |
kWh
|
$0.18 |
Electricity Demand | $119,796 | 2,972 |
kW-mo/yr
|
$40.31 |
Electricity Fees | $(-87,971.0) | - |
|
- |
Natural Gas | $90,417 | 8,946 |
MMBtu
|
$10.11 |
TOTAL YEARLY COSTS | $319,557 | |||
RECOMMENDED SAVINGS* | $572,005 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $58,727 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,084 | - |
$6,344
33,604
kWh
|
- | $(-1,260.0) | |
02 | 2.2511: Insulate bare equipment | $1,257 | $1,080 | - |
$1,257
-
MMBtu
|
- | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,734 | $3,930 |
$3,734
19,778
kWh
|
- | - | |
04 | 2.1321: Replace fossil fuel equipment with electrical equipment | $450,171 | $750,000 |
$450,171
249,600
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $26,221 | $33,106 |
$26,221
133,672
kWh
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,764 | $20,616 |
$7,764
41,121
kWh
|
- | - | |
07 | 2.1224: Replace boiler | $14,667 | $114,810 |
$1,524
8,071
kWh
|
$13,143
-
MMBtu
|
- | |
08 | 2.9114: Use solar heat to make electricty | $63,107 | $268,469 |
$63,107
334,254
kWh
|
- | - | |
TOTAL RECOMMENDED | $572,005 | $1,192,011 |
$558,865
820,100
kWh
|
$14,400
-
MMBtu
|
$(-1,260.0) | ||
TOTAL IMPLEMENTED | $58,727 | $173,542 |
$45,587
236,246
kWh
|
$14,400
-
MMBtu
|
$(-1,260.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs