Assessment Year | 2019 |
---|---|
Principal Product | walnuts |
NAICS | 311911: Roasted Nuts and Peanut Butter Manufacturing |
SIC | 2068: Salted and Roasted Nuts and Seeds |
Sales Range | $10 M to 50M |
# of Employees | 30 |
Plant Area |
150,000
ft2
|
Annual Production | 24,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $91,219 | 755,233 |
kWh
|
$0.12 |
Electricity Demand | $27,068 | 3,132 |
kW-mo/yr
|
$8.64 |
TOTAL YEARLY COSTS | $118,287 | |||
RECOMMENDED SAVINGS* | $46,457 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $44,235 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.6231: Utilize controls to operate equipment only when needed | $8,762 | - |
$8,762
72,541
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,796 | $1,080 |
$8,796
72,825
kWh
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,079 | $180 |
$1,927
15,954
kWh
|
$152
-
kW-mo/yr
|
|
04 | 2.7224: Reduce space conditioning during non-working hours | $12,409 | $1,384 |
$12,409
102,743
kWh
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $143 | $111 |
$130
1,080
kWh
|
$13
-
kW-mo/yr
|
|
06 | 3.7112: Use squeegees, mops, and vacuums for floor cleaning | $3,054 | $9,087 |
$3,054
25,289
kWh
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,214 | $49,905 |
$11,214
92,848
kWh
|
- | |
TOTAL RECOMMENDED | $46,457 | $61,747 |
$46,292
383,280
kWh
|
$165
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $44,235 | $61,456 |
$44,235
366,246
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs