ITAC Assessment: SF0542
ITAC logo
ITAC Assessment: SF0542
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product walnuts
NAICS 311911: Roasted Nuts and Peanut Butter Manufacturing
SIC 2068: Salted and Roasted Nuts and Seeds
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area 150,000
ft2
Annual Production 24,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $91,219 755,233
kWh
Electricity Demand $27,068 3,132
kW-mo/yr
TOTAL YEARLY COSTS $118,287
RECOMMENDED SAVINGS* $46,457 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $44,235

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.6231: Utilize controls to operate equipment only when needed $8,762 - $8,762
72,541
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,796 $1,080 $8,796
72,825
kWh
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,079 $180 $1,927
15,954
kWh
$152
-
kW-mo/yr
04 2.7224: Reduce space conditioning during non-working hours $12,409 $1,384 $12,409
102,743
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $143 $111 $130
1,080
kWh
$13
-
kW-mo/yr
06 3.7112: Use squeegees, mops, and vacuums for floor cleaning $3,054 $9,087 $3,054
25,289
kWh
-
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,214 $49,905 $11,214
92,848
kWh
-
TOTAL RECOMMENDED $46,457 $61,747 $46,292
383,280
kWh
$165
-
kW-mo/yr
TOTAL IMPLEMENTED $44,235 $61,456 $44,235
366,246
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs