| Assessment Year | 2019 |
|---|---|
| Principal Product | almonds |
| NAICS | 311911: Roasted Nuts and Peanut Butter Manufacturing |
| SIC | 2068: Salted and Roasted Nuts and Seeds |
| Sales Range | $50 M to 100M |
| # of Employees | 241 |
| Plant Area |
290,000
ft2
|
| Annual Production | 60,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,053,168 | 11,549,814 |
kWh
|
$0.091 | |
| Electricity Demand | $364,677 | 23,952 |
kW-mo/yr
|
$15.23 | |
| Natural Gas | $204,568 | 25,704 |
MMBtu
|
$7.96 | |
| Waste Disposal Costs | |||||
| Water Usage | $17,112 | 749 |
Tgal
|
$22.84 | |
| TOTAL YEARLY COSTS | $1,639,525 | ||||
| RECOMMENDED SAVINGS* | $508,453 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $96,672 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $146,044 | - | - | - | $146,044 | - | |
| 02 | 2.2621: Modify refrigeration system to operate at a lower pressure | $29,680 | $12,500 |
$29,680
325,507
kWh
|
- | - | - | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $15,353 | $5,947 |
$5,196
56,988
kWh
|
- | - |
$10,157
-
MMBtu
|
|
| 04 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $27,526 | $16,915 |
$31,896
349,814
kWh
|
$7,293
-
kW-mo/yr
|
- |
$(-11,663.0)
-
MMBtu
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,440 | $7,616 |
$11,440
125,465
kWh
|
- | - | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,101 | $5,998 |
$8,101
88,849
kWh
|
- | - | - | |
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $25,533 | $34,367 |
$20,781
227,915
kWh
|
$4,752
-
kW-mo/yr
|
- | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,565 | $11,649 |
$5,343
58,601
kWh
|
$1,222
-
kW-mo/yr
|
- | - | |
| 09 | 2.9114: Use solar heat to make electricty | $238,211 | $1,672,972 |
$219,812
2,410,750
kWh
|
$18,399
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $508,453 | $1,767,964 |
$332,249
3,643,889
kWh
|
$31,666
-
kW-mo/yr
|
$146,044 |
$(-1,506.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $96,672 | $78,077 |
$80,541
883,325
kWh
|
$5,974
-
kW-mo/yr
|
- |
$10,157
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs