ITAC Assessment: SF0522
ITAC logo
ITAC Assessment: SF0522
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Wine
NAICS 312130: Wineries
SIC 2084: Wines, Brandy, and Brandy Spirits
Sales Range greater than $500
M
# of Employees 310
Plant Area 2,310,000
ft2
Annual Production 29,719
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,715,632 20,802,483
kWh
Electricity Demand $423,823 46,728
kW-mo/yr
Natural Gas $188,090 20,235
MMBtu
TOTAL YEARLY COSTS $2,327,545
RECOMMENDED SAVINGS* $979,364 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $235,127

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.5195: Change product design to reduce energy requirements $148,377 - $148,377
1,799,165
kWh
- - - - -
02 3.1191: Change procedures / equipment / operating conditions $12,924 - $12,924
156,708
kWh
- - - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $13,732 $560 $9,263
112,318
kWh
$4,469
-
kW-mo/yr
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,705 - $5,965
72,332
kWh
- - - $(-1,260.0) -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,703 $630 $1,465
17,760
kWh
$238
-
kW-mo/yr
- - - -
06 2.7224: Reduce space conditioning during non-working hours $2,306 $1,047 $342
4,145
kWh
- $1,964
-
MMBtu
- - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $56,281 $52,606 $48,631
589,685
kWh
$7,650
-
kW-mo/yr
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $213,278 $289,618 $157,660
1,911,081
kWh
$35,428
-
kW-mo/yr
- $15,934 $4,256 -
09 2.2511: Insulate bare equipment $947 $1,332 - - $947
-
MMBtu
- - -
10 2.4224: Upgrade controls on compressors $14,838 $29,848 $14,838
179,918
kWh
- - - - -
11 2.2621: Modify refrigeration system to operate at a lower pressure $113,493 $259,859 $113,493
1,376,178
kWh
- - - - -
12 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,563 $26,446 $10,563
128,088
kWh
- - - - -
13 2.2628: Utilize a less expensive cooling method $38,069 $123,450 $32,959
399,647
kWh
$5,110
-
kW-mo/yr
- - - -
14 4.212: Adopt in-house material generation $348,148 $1,184,880 - - - - - $348,148
TOTAL RECOMMENDED $979,364 $1,970,276 $556,480
6,747,025
kWh
$52,895
-
kW-mo/yr
$2,911
-
MMBtu
$15,934 $2,996 $348,148
TOTAL IMPLEMENTED $235,127 $320,513 $178,805
2,167,476
kWh
$35,428
-
kW-mo/yr
$1,964
-
MMBtu
$15,934 $2,996 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs