| Assessment Year | 1995 |
|---|---|
| Principal Product | Integrated microcircuits |
| NAICS |
n/a
|
| SIC | 3674: Semiconductors and Related Devices |
| Sales Range | $100 M to 500M |
| # of Employees | 600 |
| Plant Area |
150,000
ft2
|
| Annual Production | 100,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $907,143 | 23,922,919 |
kWh
|
$0.038 |
| Natural Gas | $150,248 | 46,805 |
MMBtu
|
$3.21 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $52,310 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $44,740 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,640 | $54,100 |
$20,640
499,121
kWh
|
- | - | |
| 02 | 3.4115: Recover and reuse cooling water | $18,410 | $2,190 | - |
$8,460
-
Tgal
|
$9,950
-
Tgal
|
|
| 03 | 2.4133: Use most efficient type of electric motors | $5,690 | $7,000 |
$5,690
147,714
kWh
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $3,030 | $2,280 |
$3,030
148,007
kWh
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,860 | $4,470 |
$1,860
44,842
kWh
|
- | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $1,690 | $470 |
$1,690
46,600
kWh
|
- | - | |
| 07 | 2.4131: Size electric motors for peak operating efficiency | $990 | $10,410 |
$990
24,033
kWh
|
- | - | |
| TOTAL RECOMMENDED | $52,310 | $80,920 |
$33,900
910,317
kWh
|
$8,460
-
Tgal
|
$9,950
-
Tgal
|
||
| TOTAL IMPLEMENTED | $44,740 | $63,290 |
$26,330
646,835
kWh
|
$8,460
-
Tgal
|
$9,950
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs