| Assessment Year | 1996 |
|---|---|
| Principal Product | telephone directories |
| NAICS |
n/a
|
| SIC | 2741: Miscellaneous Publishing |
| Sales Range | $100 M to 500M |
| # of Employees | 400 |
| Plant Area |
270,000
ft2
|
| Annual Production | 50,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $325,917 | 19,966,003 |
kWh
|
$0.016 |
| Electricity Demand | $612,049 | 39,247 |
kW-mo/yr
|
$15.59 |
| Electricity Fees | $264 | - |
|
- |
| Natural Gas | $129,652 | 37,963 |
MMBtu
|
$3.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,694 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,603 | $27,027 |
$3,723
228,605
kWh
|
$4,880
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $761 | $883 |
$353
21,688
kWh
|
$408
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $3,320 | $2,700 |
$1,440
88,218
kWh
|
$1,880
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,690 | $2,180 |
$1,170
72,098
kWh
|
$1,520
-
kW-mo/yr
|
- | - | - | |
| 05 | 3.8132: Use less toxic and volatile solvent substitutes | $2,070 | $3,520 | - | - |
$3,240
-
gal
|
- | $(-1,170.0) | |
| 06 | 3.6192: Use a less expensive method of waste removal | $1,250 | - | - | - | - |
$1,250
-
lb
|
- | |
| TOTAL RECOMMENDED | $18,694 | $36,310 |
$6,686
410,609
kWh
|
$8,688
-
kW-mo/yr
|
$3,240
-
gal
|
$1,250
-
lb
|
$(-1,170.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs